Corporate IT Office — Hinjewadi Phase 2
Scope
Complete MEP and interior fit-out including HVAC, electrical, plumbing, fire fighting, false ceiling, glass partitions, and modular workstations.
Challenge
Tight 14-week handover window with live building constraints and phased occupancy requirements.
Solution
Prefabricated MEP modules, parallel civil-MEP tracks, and night-shift ceiling works in occupied zones.
Materials
VRF systems, GI insulated ducts, modular furniture, gypsum partitions with acoustic insulation.
Execution
Weekly coordination meetings with PMC, BIM clash review at Week 2, and staged testing by floor.
Safety
Hot work permits, height safety harnesses, and fire watch during commissioning.
Outcome
LEED-ready MEP infrastructure with 18% lower HVAC energy vs baseline design.
Benefits
Client achieved early move-in, reduced rental overlap, and scalable floor plate for 200 additional seats.